Church Building Project
Updated!!
Roof is completed and Steeple is up!
History of the project
In July 2013—
God has blessed us with a property in Point Cross on the outskirts of Cheticamp. It has 19 acres with a 40? X 28? building with 2 floors with access to sewage and water. Three years ago we started saving for a church home for our congregation. We had saved up $40,000 in free will giving plus some operating money. This property was for sale last year for $99,000. It dropped to $65,000 this spring and we prayed and offered $40,000 and the seller accepted with expenses on top of that.
While we know that the church is the people (not the building) it is wonderful to have a building of our own to meet in. Through the hard work and guidance and provision of God we can rejoice in being in our own building.
Upstairs when we bought it
The second floor was partly insulated with some gyp-rock up. This insulation all needed to come down and the gyp-rock thrown out. The space for insulation was too narrow so we had to deepen all the rafters by adding about 4 inches and strap it all. There was also rot under the windows and under big double doors that were upstairs. This rot went down to the 1st floor. We removed those doors and windows and fixed the walls on both ends. This involved removing siding and replacing studding and plywood on both ends. We put a new exit door upstairs reinstalled windows and re-insulated some of it.
We also had an electrician come in and rewire all the upstairs and the downstairs
New door and windows and siding!
As of Jan 1st 2017
Here is what has been done and some things that will need to be done in the near future
We have worked as God provided the finances and He has provided wonderfully!
The white text items are done
The green text indicates what is yet to be done
- Electrical hook-up with Nova Scotia Power with a new mast and entrance
- Wire the entire building for new lights and plugs and electric heat
- Take out all existing s ofhelving and old wallboard
- Replace a section of wall that had rot in it from window leakage
- Install a new exit door at the back of the building
- Remove the old door and window on the right side of the building and close it in
- Frame up 2 bathrooms downstairs
- Extend the roof rafters out to increase the insulation and strap the entire surface for wall board.
- A new exit door for upstairs installed
- Hook up to the existing septic system and waterline to the well (Pump is already there)
- Remove 2 garage doors and disassemble and close in the wall
- New Fridge donated
- counter and sink purchased
- Chairs and a sign were donated from Belle Cote Community Center
- Remove steel chimney and close in the roof
- Repair the wall that has rot in it on the left side of the building and close in the big door upstairs
- New windows on the front of building
- Install a new entrance door with panic bar
- New siding on the front of building
- Brace the floor joists on the ceiling and strengthen the main beams to meet code
- Frame up bathroom upstairs
- Finish electrical and sound system wiring and get inspection
- An outside stairway from the upstairs for a fire exit
- Venting for air exchanger
- Install air exchanger
- Install plumbing for bathrooms and toilets and sinks including venting
- Insulate the upstairs ceiling and walls
- Insulate the downstairs ceiling and walls
- Install a drop ceiling with new light panels
- Wallboard the entire downstairs
- Wallboard the entire upstairs
- Drywall Taping
- Install sound booth
- Floor leveller to put on concrete floor and insulated panels to be put on concrete
- Install sub floor
- New industrial tile flooring
- Paint Inside of building
- Install cupboards and shelves and stove for kitchenette
- Close in the inside stairwell
- fire door installed to upstairs
- Install Electric heaters throughout the building
- Install toilets sinks in 2 washrooms and hot water tank
- Purchase tables
- Fix the driveway so that it is not too steep
- More surface gravel work to be done on driveway
- Install a permanent sign at the road
- Install Shower
- New roof
- Place a steeple on the building to increase visibility
- Install 2 heat pumps for summer air conditioning and winter heat